iCDMA · Highway (time-based)
Day 1 · Tue 2009-06-09
SunnyPlanned: $2,249,358 by day 101
Spent: $0 · site space 0/800
Schedule
planned in progress complete critical path
Cumulative cost
Today's decisions
1_Strip Topsoil(a)0%
Crews: 100% pace · $12,565/day — hire or fire
i69_act1_crew1 $12,565/day
⚙ Backhoe Loader $323/d1/1
⚙ Dump Truck $586/d4/4
Equipment Operator $512/d2/2
⚙ Hyd Excavator $952/d1/1
Worker $392/d11/11
Foreman $417/d5/5
Truck Driver $381/d4/4
Staffing resets to the full complement each morning. Fewer hands slow the pace; extra hands cost full wages at 80% effectiveness.
Events
Nothing has gone wrong. Yet.