iCDMA · Road (CPM staging)

Day 1 · Tue 2009-06-09

Sunny
Planned: $107,368,152 by day 61
Spent: $0 · site space 0/1200
Schedule
115294357today1_Strip Topsoil0%2_Remove Concrete Pavemen…0%2_Remove Concrete Pavemen…2_Remove Concrete Pavemen…4_Install Drainage(a)4_Install Drainage(b)4_Install Drainage(c)3_Grade Subbase(a)3_Grade Subbase(b)3_Grade Subbase( c)5_Place OGDC Mainline(a)5_Place OGDC Mainline(b)5_Place OGDC Mainline( c)6_Pave E.B Mainline(a)6_Pave E.B Mainline(b)6_Pave E.B Mainline( c)7_Place OGDC Ramps and Ga…8_Pave E.B Ramps and Gaps9_Place Gravel Shoulder10_Slope Grading and Rest…11_Stripe to Open Pavemen…12_Relocate Barrier Wall13_Re-stripe W.B. 14_All Lanes Open
planned in progress complete critical path
Cumulative cost
$28.2M$56.4M$84.6M$112.7Mday 61plannedprojected
Today's decisions
1_Strip Topsoil0%
Crews: 100% pace · $19,029/day — hire or fire
i69_act1_crew1 $12,565/day
Backhoe Loader $323/d1/1
Dump Truck $586/d4/4
Equipment Operator $512/d2/2
Hyd Excavator $952/d1/1
Worker $392/d11/11
Foreman $417/d5/5
Truck Driver $381/d4/4
i69_act1_crew2 $6,464/day
Worker $392/d12/12
Foreman $417/d3/3
Pickup $128/d1/1
Truck Driver $381/d1/1
Staffing resets to the full complement each morning. Fewer hands slow the pace; extra hands cost full wages at 80% effectiveness.
2_Remove Concrete Pavement(a)0%
Crews: 100% pace · $25,305/day — hire or fire
i69_act2_crew1 $6,215/day
Attenuator Truck $317/d1/1
Backhoe Loader $323/d1/1
Equipment Operator (light) $470/d2/2
Equipment Operator (medium) $497/d1/1
Hyd Excavator $952/d1/1
Worker $392/d6/6
Foreman $417/d2/2
i69_act2_crew2 $19,090/day
Backhoe Loader $323/d1/1
Driver $393/d12/12
Dump Truck $586/d12/12
Equipment Operator (light) $470/d1/1
Equipment Operator (medium) $497/d1/1
Front end Loader $595/d1/1
Hyd Hammer $168/d1/1
Worker $392/d8/8
Foreman $417/d5/5
Pavement Removal Bucket $62/d1/1
Staffing resets to the full complement each morning. Fewer hands slow the pace; extra hands cost full wages at 80% effectiveness.
Events
Nothing has gone wrong. Yet.